I. General

1.01 Description of the Diamond 105 System

Diamond AdThe Diamond 105 Non-Penetrating Roofing System is a unique EPDM singly ply roofing system. The EPDM membrane is mechanically fastened to the roof deck by means of the patented 105 System plate. The 105 System plate is fastened to the deck beneath the EPDM membrane thus giving a true non-penetrating roofing system.

The patented 105 System plate is a 7″ x 7″ composite plate consisting of the following:

A .060 EPDM sheet, factory laminated to a .030 elastomeric tape, a 4″ 16 gauge galvanized steel disk adhered to the elastomeric tape, and a.030 elastomeric tape adhered on top of the steel disk. The plates are available with a 1″ center hole for use with auger screws or ¼” counter sunk center hole for fastening with steel screws. The top of the plate is covered with a release paper.

The Diamond 105 System is available in .045 or .060 inch EPDM sheets.

1.01-1
The Diamond 105 System must be installed in strict accordance with specifications approved by International Diamond Systems, Toledo, Ohio.

1.01-2
The Diamond 105 System must be installed using recognized safety standards and procedures for the products used. Material Safety Data Sheets will be provided as prescribed by law.

1.02 Submittals

1.02-1
A dimensional drawing of the overall roof showing penetrations, drains, perimeter details, etc. must be furnished to IDS. Flashing details as used must be done according to approved details in this manual.

1.02-2
No deviation shall be made from IDS specifications or the approved roof drawings without prior written permission of IDS.

1.02-3
When field conditions require changes, Qualified Contractors are to supply IDS with as-built construction drawings.

1.03 Material Storage an Handling

1.03-1
Keep all materials stored in their original unopened containers.

1.03-2
Keep all containers of adhesives, cleaners, and primers in areas away from sparks, open flames and excessive heat. Always use proper protective equipment when handling hazardous materials.

1.03-3
Store all materials between 60 and 80 degrees F. Start work with adhesives, sealants and tape products at temperatures between 60 and 80 degrees F.

1.03-4
Store all adhesives, sealants and tape products in a dry area protected from water and direct sunlight. Damaged material will be replaced at the contractors expense.

1.04 Site Conditions

1.04-1
Do not use bitumen base, coal tar base, oil base or plastic roof cements.

1.04-2
Do not install directly onto low melting point asphalt.

1.04-3
Do not allow waste products (petroleum, grease, oil, solvents, animal fat, etc.) or direct steam to come in contact with the IDS System. Present any exposures not typical for normal installation to IDS for assessment of impact to the roof systems total performance.

1.04-4
Do not install EPS roof insulation directly onto coal-tar roof surface.

1.04-5
Protect all material and components from direct contact with steam or heat sources in excess of 180 degrees F.

1.04-6
Splicing and bonding surfaces must be clean and dry.

1.04-7
Adhesives, sealants and primers and their fumes contain petroleum distillates and therefore are Extremely Flammable. Do not breathe vapors for extended periods. Avoid use near fire or other heat sources. Do not place open containers near fresh-air intake ventilators. Consult container labels and Material Safety Data Sheets for specific information.

1.04-8
Roof surface must be free of ponded water, ice and snow prior to application. The roof surface should be designed to be water-free within 48 hours after precipitation.

1.04-9
Do not apply IDS roof systems in inclement weather. High humidity at lower temperatures may cause moisture to condense and freeze. Do not apply systems when these conditions exist.

1.04-10
The minimum roof slope will be determined by the building owner or his designee. IDS recommends a minimum roof slope of 1/8 inch per horizontal foot.

1.05 Quality Assurance

1.05-1
IDS roofing materials must be applied by an approved applicator. It is the building owner’s responsibility to select a qualified, approved contractor. International
reserves the right to refuse approval.

1.05-2
As IDS reserves the right to revoke approval without notice, it is the building owner’s responsibility to verify his qualified roofer’s status.

1.05-3
If a warranty is requested, the approved applicator must certify that all IDS products have been installed according to applicable specifications and details. After certification, an IDS technical representative will visually inspect the roofing system and materials. This inspection is not certification that all conditions on the roof and all elements of the roofing system are in conformance with IDS specifications. IDS is not responsible for the products of others or conditions not discoverable by visual inspection.

1.05-4
It is the building owner’s responsibility to have sufficient knowledge to interpret all specifications in this manual.

1.05-5
These specifications are in lieu of all other specifications, written or implied.

1.05-6
Building codes are above and beyond the intended purpose of these specifications. IDS cannot be responsible for adherence to local building codes. It is the responsibility of the building owner or his designee to notify IDS of local requirements.

1.06 Warranty

1.06-1
A membrane systems warranty is available for commercial and industrial buildings within the United States and Canada and applies only to the products supplied by IDS.

1.06-2
Installation subjected to conditions not typical are not warrantable.

1.06-3
IDS is not responsible for the cleanliness or the discoloration of the roofing membrane caused by conditions including, but not limited to, dirt, pollutants or biological agents.
IDS is not responsible for acts of God or vandalism, etc.

1.06-4
IDS assumes no liability for internal moisture. Changes or repairs made to the roofing system without prior written authorization from IDS will void the warranty.

1.06-5
To obtain the IDS warranty, fill out the Request for Warranty form certifying the roof has been installed according to IDS specifications and that the building owner or his designee have approved all specifications.

1.06-6
The roofing contractor is responsible for workmanship for a period of two (2) years from the issue date of the warranty.

1.06-7
For more detailed information, please refer to the warranty section of this manual.

ll. Products

2.01 Product Statement

2.01-1
All components of the Diamond 105 roofing system are to be products of IDS or accepted and approved, in writing, by IDS.

2.01-2
Products by other manufacturers are not covered by the IDS warranty. See Full System Warranty for exception.

2.02 Membrane

2.02-1
IDS EPDM, .045 or .060 inches thick is available in widths of 5, 7, 10, 20, 30, 40, and 50 feet and in lengths of 50 or 100 feet.

2.03 Insulation

2.03-1
A minimum of ½” of approved insulation board must be placed over the existing substrate. Insulation that is placed directly onto metal deck must be of proper density and thickness to support normal traffic and meet building and fire codes.

2.03-2
Install only as much insulation as can be covered and completed before the end of the day or before inclement weather.

2.03-3
Stagger insulation joints when installing multiple layers.

2.03-4
Contact IDS for specific insulation restrictions.

2.04 Fasteners

2.04-1
On-site tests should be performed by an independent laboratory to determine the actual pullout values of possible fasteners.

2.04-2
Refer to section 3.02 and section 7 of this manual for specific fastener information.

Note: Only domestic steel fasteners are approved for use with IDS roofing systems. All fasteners must be tested and approved by Factory Mutual prior to approval for use by IDS. Contact IDS for complete list of approved fasteners.

2.05 Attachment Plates

2.05-1
Insulation plates and fasteners must be tested by Factory Mutual and accepted by IDS prior to project bid and installation.

2.05-2
The Diamond 105 System shall use only the patented 7″ x 7″ self-adhering 105 Plates as supplied by IDS. No other attachment plates are acceptable.

lll. Execution

3.01 Inspection and Preparation for New Construction

3.01-1
It is the building owner or his designee’s responsibility to provide adequate decking for the application of the IDS roofing system.

3.01-2
The roofing contractor shall confirm the structural integrity of the existing deck and specify replacement or repair as required.

3.01-3
Fluted metal decks require an overlayment rigid enough to withstand the traffic to which the roof may be subjected.

3.01-4
New membrane substrate must be clean, dry, smooth, free of sharp edges, loose or foreign materials. Gaps greater than ¼ inch must be filled with appropriate material.

3.01-5
Wood nailers shall be pressure treated #2 lumber or better. Wood nailers treated with asphalt or creosote are not acceptable.

3.02 Roof Deck Criteria

3.02-1
The roofing contractor shall confirm the structural integrity of the roof deck and replace or repair as required.

3.02-2
22 Gauge metal
Due to the fluted design of most metal decks, a specific effort is required to insure ¾ inch deck penetration by all fasteners. Pre-bid investigation of deck alignment, physical conditions and rib depth is recommended. Pullout resistance of minimum 360 pounds is
required.

3.02-3
Structural concrete
Rated at 3000 psi or greater, into which at least 1 inch penetration is possible.
Fasteners must penetrate the deck a minimum of 1 inch and a maximum of 1 ½ inches.
Structural concrete requires the drilling of pilot holes.

Due to wide variations in “structural
concrete”, only on-site trial of drill bits and fasteners can determine
compatibility. Pull-out resistance of 800 pounds minimum is required.

3.02-4
Cement-Wood Fiber and Gypsum
Use IDSs’ Liquid Auger Seal Screw. Pull-out resistance of 360 pound minimum required.

3.03 Execution (Retrofit)

3.03-1
All wet insulation and substrate must be removed. Depressions or holes must be filled with an appropriate material.

3.03-2
Sprayed in-place urethane foam is not an approved substrate for IDS systems.

3.03-3
When re-roofing over single-ply membranes:

  1. Cut and ventilate the existing membrane to avoid moisture
    build up.
  2. Substrate must be dry, clean, smooth, free of sharp edges,
    loose and foreign material.
  3. A minimum ½ inch recovery board or approved insulation is
    required.

3.03-4
IDS recommends consulting the S.P.R.I.’s most recently published guidelines for retrofitting existing roof systems.

3.03-5
When re-roofing over existing BUR:

  1. A minimum ½ inch recovery board or approved insulation is required.
  2. IDS requires all gravel surfaces be vacuumed or power broomed for removal from the substrate. This will eliminate the excess weight and avoid vertical instability of the recovery board or insulation, which could result in the attachment screw penetrating the membrane.
  3. Before final application of the system the substrate must be dry, clean, smooth, free of sharp edges, loose and foreign material.

3.04 Tear – Off

3.04-1
The roofing contractor must confirm the structural integrity of the roof deck and repair or replace as required.

3.04-2
It is the building owner or his designees responsibility to provide adequate decking for the application of IDS systems.

3.04-3
Fluted metal decks require an overlayment rigid enough to withstand the traffic to which the roof may be subjected.

3.04-4
Tear off all existing material. The substrate must be dry, clean, smooth, free of sharp edges, loose and foreign material. Gaps greater than ¼” must be filled with
appropriate material.

3.04-5
All decks must meet or exceed Factory Mutual pull-out test requirements.

3.05
Installation of the Diamond 105 System

3.05-1
Insulation Attachment

Install 4’ x 8’ sheets of an approved insulation board. Insulation fasteners must be installed on all four corners of the insulation board 12″ from each corner. (Refer to D-1)

The 105 System requires a one row perimeter
of plates as follows:

  1. Gutter edge:
    Starting from the gutter edge, the perimeter row of 105 plates will be placed 1 foot from the edge 12″ on center. (Refer to D-2)
  2. Parapet wall:
    The perimeter row of 105 plates must be placed at the base of the parapet wall directly on the substrate 12″ on center.
    105 plates should always be installed flat on the substrate. (Refer to D-2)
  3. Diamond Pattern Layout:
  1. Install Diamond 105 Plates on all 4 corners of the 4’ x 8’ insulation.
  2. Install Diamond 105 Plates along the 8’ edge of the insulation halfway between the corner plates.
  3. Install Diamond 105 Plates in the center of the 4’ x 4’ pattern created in steps 1 & 2. Refer to details at the end of this section for specific fastening requirements.

3.05-2 Membrane Placement

  1. Roll out and position the membrane and allow to relax for a minimum of 30 minutes.
  2. Fold the membrane back halfway and apply activator sparingly to the membrane with a sponge mop in line with the 105 Plates. Allow the activator to dry.
  3. Once the activator has dried remove the release paper from the 105 Plates and float the membrane over the exposed plates. Remove release paper and recover one row of plates at a time to avoid unnecessary wrinkling of the membrane.
  4. To insure proper mating of the plates to the membrane apply pressure with a steel tile roller or a stiff bristled push-broom.
  5. Temporary closures and night seals that ensure moisture does not damage the roofing system are the responsibility of the roofing contractor. (See Nite-Seal)

3.05-3 Membrane Splicing

A. Seam Tape

  1. Fold back the top sheet to allow cleaning of both surfaces. Clean both surfaces with clean natural fiber rags, dampened, but not saturated with Splice Cleaner. Turn rags frequently and replace often. Particular attention should be given to factory splices to remove excessive amounts of dusting agent. The splice area must be free of any foreign material that may interfere with ultimate bonding.
  2. Stir Activator thoroughly before and during use. Apply Activator sparingly to both sides of the seam lap with a sponge mop. Allow the Activator to dry completely before proceeding. Drying time may vary due to weather conditions.
  3. When applying seam tape, allow 1/8 to ¼ inch overlap on the outside edge of the top lap of the EPDM. Before the release paper is removed from the tape roll with a steel roller perpendicular to the seam. After rolling, remove the release paper and mate the two surfaces. Roll the completed seams. No caulking is needed.
    Note: An additional piece of seam tape will be needed at all cross seams. Always avoid back water seams.
  4. Flash all seams at change in direction in accordance with detail l-25.

details-1-25

B. Splice adhesive

  1. Position the membrane to overlap a minimum of 4 inches. Fold the top sheet back to allow for cleaning of both surfaces to be spliced.
  2. Clean both surfaces using clean rags with International Splice Cleaner to remove all dusting agent, dirt, and other contaminants that will affect the completed splice. Allow to dry. Repeat as necessary to assure that the membrane is completely clean. Change rags frequently.
  3. Thoroughly stir International Butyl Splice Adhesive before and during use. Apply the Splice Adhesive using a 3″ – 4″ wide solvent resistant brush in an even, smooth coat with long painting type strokes. Apply the Splice Adhesive to both surfaces at about the same time to allow equal drying. Apply at specified coverage rate.
    Note: Do Not use circular motions when applying Splice Adhesive. Do Not use paint rollers, spray equipment, or other mechanical equipment for application of Splice Adhesive.
  4. Allow the Splice Adhesive to flash off. Touch the Splice Adhesive with a clean, dry finger to be sure that the adhesive is dry. If the Splice Adhesive is dry none will transfer to your finger. If adhesive transfers the splice is not ready for mating and should not be closed. Flash off time will vary due to weather conditions.
  5. Roll the top sheet toward the bottom sheet until it falls freely into place so as not to stretch or wrinkle the membrane.
  6. Apply pressure by brushing your hand across the entire length of the seam. Roll the seam using a 1 ½” – 2″ wide silicone or hand roller, roll the entire splice toward the outside edge of the splice then along the entire length of the splice.
  7. Install T-Joint lap covers at all field seam and flashing intersections. Install flashing at horizontal to vertical direction change.
  8. Wait a minimum of 4 hours and 24 hours maximum if weather permits before caulking with Lap Sealant. If weather is threatening apply Lap Sealant before leaving the project. Apply Lap Sealant in a continuous bead 3/8″ to ¼” wide along the length of the seam. Using the supplied Lap Sealant tool, feather immediately, be sure to leave an adequate amount of Lap Sealant directly over the splice edge.

3.05-4 Base
Tie In

Secure membrane at all locations where the membrane terminates or changes angles more than 2 inches in 12 inches (curbs, roof edge, interior walls, etc.) except for pipe penetrations less than 18 inches in diameter or, square penetrations less than 6 inches square.

  1. Install Diamond 105 Plates in accordance with details and specifications in this manual.
  2. See System section to determine
    applicable Perimeter Base Attachment method or contact International.

3.05-5
Flashing & Details

A. Parapet Walls, Curbs, Skylights, Etc.

  1. Mechanically fasten 5/8″ exterior grade or pressure treated plywood in accordance with the project designers specifications over the following substrates.
    1. Textured Masonry
    2. Gypsum or Gypsum Board
    3. Stucco
    4. Corrugated Metal
    5. Any Uneven Substrate
  2. Remove old, loose or unsecured flashing and excessive amounts of asphalt to provide a smooth surface for the new flashing.
  3. Splice between flashing and the field sheet using Splice Adhesive or Seam Tape prior to adhering to the vertical surface. USE CURED MEMBRANE WHENEVER POSSIBLE. See DETAILS.
  4. Apply Bonding Adhesive to the vertical surface and flashing at the same time to allow for the same amount of flashing off time. Apply Bonding Adhesive using a roller.
  5. Allow Bonding Adhesive to dry until tacky to the touch. Test readiness by touching with a clean, dry finger. If the Bonding Adhesive is dry no adhesive
    will transfer to the finger. Flash off time will vary due to weather conditions.
  6. Roll the flashing up the wall into the adhesive being careful to minimize wrinkling.
  7. Broom the flashing using a stiff bristled push broom. When using Uncured Flashing roll with a hand roller.
  8. Terminate in accordance with applicable details.
  9. Cover T-Laps with a minimum 7″ x 7″ Cover Tape. Roll T-Lap Cover with a hand roller.

B. Metal Drip Edges & Gutter Flanges.

  1. Seven (7) inch wide by 100 feet long Cover Tape should be used to flash metal drip edge and gutter flanges. Never use it to flash seams at angle changes. Never use it as a substitute for Uncured Flashings.
  2. Clean the metal and the membrane with clean rags, dampened but not saturated with Splice Cleaner. Turn rags frequently and replace often. Particular attention should be given to factory splices to remove excessive amounts of dusting agent. Allow the Splice Cleaner to flash-off.
  3. Stir Activator thoroughly before and during use. Apply activator sparingly to the metal and the membrane using a sponge mop. Allow Activator to dry until all solvent has completely flashed-off.
  4. Apply the Cover Tape so that a minimum of 3 inches extends onto the membrane and a minimum of 3 inches onto the metal. An additional piece of Uncured Flashing is required at all metal edge overlaps where the Cover tape does not completely cover the metal edge.
  5. Roll Cover Tape with a steel hand roller perpendicular to the edge.